Procedure for establishing a
Wind Farm |
| |
| The application
should contain the following: |
| |
|
|
Capacity of wind power project. |
|
|
Project
location. |
|
|
Documentary evidence showing intentions
to purchase land. |
|
|
Proposed evacuation facilities at site. |
|
|
Source of finance (loan, equity
etc.). |
|
|
Organizational capability. |
| |
|
|
| Recommendation
by State Government regarding: (*) |
| |
|
|
Allotment from state government. |
|
|
Purchase/allotment of land. |
|
|
Evacuation approval from
State Electricity Board. |
|
|
Approval of construction drawings from
CEIG. |
|
|
Construction at site. |
|
|
Safety certificate from
CEIG. |
|
|
Grid synchronization approval from
State Electricity Board. |
|
|
Signing of
PPA or banking & Wheeling Agreement. |
|
|
Obtaining necessary clearance &
approvals from State/Central Government. |
| |
|
|
| Project
organization: |
| |
|
|
Selection of potential sites. |
|
|
Contour and plain table survey. |
|
|
Site analysis. |
|
|
Micrositing. |
|
|
Computation of probable energy outputs. |
|
|
Acquisition of land. |
|
|
Preparation of feasibility and detailed
project report. |
|
|
|
|
| (*)
Can vary from State to
State
|
 |
|